Project Timeline

Eastern Avenue Road Reconstruction Project from I-215 to Serene Avenue on Monday, May 29 at 9 p.m. The work is scheduled to take approximately four weeks. Working hours will be 9 p.m. to 6 a.m. from Sunday through Friday. See Full Release

Project Start Date: April 21



Please note: The following timeline includes the primary project work schedule. Adjustments to the schedule, when applicable, are noted above.
  • Phase 1: I-215 Ramps

    Work days:
    Sunday – Thursday
    Work hours:
    9:00 p.m. to 6:00 a.m.
    Anticipated ramp closures – over three weekends
    No more than one ramp closed per weekend – reopened by Monday at 6 a.m.
  • Phase 2: Eastern Ave – Serene to I-215 Underpass & Robindale Sewer

    Work days:
    Sunday – Thursday
    Work hours:
    9:00 p.m. to 6:00 a.m.
    At least one lane open to traffic in each direction during night operations
    At least two lanes open to traffic in each direction between 6 a.m. and 9 p.m. and weekends
  • Phase 3: Eastern Ave – Wigwam to Warm Springs

    Work days:
    Monday – Friday
    Work hours:
    7:00 a.m. to 3:30 p.m.